Last Thursday I met up with a good friend from the Data Centre industry who has run more Data Centre floors than he’s had hot dinners. With more than 25 years in Data Centres behind me there was only one subject we would end up complaining about, the weather, well I am from the UK (too warm, which I am told is possible). Soon the subject has changed as a phone was slid the table with the headline: “Bowen’s told the Data Centres they’ve got to bring their own power.”
My first thought was a BYO restaurant. Only instead of turning up with a bottle of Shiraz, you rock up with a wind farm and a whacking great battery. As it turns out, that isn’t far off.
What has actually changed
Last week the Australian Energy Market Commission (AEMC), the rule-maker for our electricity market, published two rule change requests from Energy Minister Chris Bowen. Together they would put a mandatory contracting obligation on large Data Centres. Put simply, they would need to show that their electricity demand is backed by enough firmed supply to match their load profile.
“Firmed” is the important word. Put nicely: it’s renewable power that still turns up when the sun has gone down and the wind has dropped, because it’s backed by something else. In the UK we’d call that having a plan for when it rains, which is always.
What counts as firming is broader than many people expect. Power purchase agreements, cap contracts, tolling agreements, batteries behind the meter and demand response would all be eligible. Compliance would be judged across the operator’s whole portfolio, not contract by contract. There’s one important catch: the resources must sit in the same National Electricity Market (NEM) region as the Data Centre. You can’t buy a solar farm in Queensland to cover a hall in Western Sydney.
The rules also have teeth. Operators that fall short would face enforcement by the Australian Energy Regulator or AEMO, including financial penalties. In the worst case, a Data Centre could be required to cut its demand until it can show the cover. Load shedding a Data Centre is like telling the pub to stop pouring at half-time in a State of Origins match. You really don’t want to be the one who has to make that announcement.
The A$40 billion question
Why go this far? Some recent modelling from the Smart Energy Council found that if around 5GW of new Data Centre load connects from July 2028 without matching new supply, wholesale electricity costs across the eastern states could rise by about A$40 billion over six years.
The more uncomfortable number is who pays. Around A$37 billion of that would fall on everyone other than the Data Centres. Households would carry roughly A$9.2 billion, with business and industry covering most of the rest. Queensland would be hit hardest, at nearly A$20 billion, because that’s where most of the modelled new load lands.
To be fair to the Council, it is upfront that this is a “stress test, not a forecast”. It only covers wholesale costs, not network charges, and it gives no credit for Data Centres operating flexibly. The Council also estimates that around 90% of the household impact disappears if new Data Centres are matched with new renewables and storage. That is exactly what the proposed rules are designed to achieve.
So this isn’t a case of “Data Centres bad”. It’s “Data Centres, pay for your own round”.
Why it’s happening now
The short answer is scale. AEMO expects Data Centre consumption to rise from about 5TWh this year to 34TWh by 2035-36, taking it from roughly 3% of grid demand to 13%. The federal government talks about an investment pipeline worth more than A$150 billion.
The longer answer is timing. A Data Centre can be built in two or three years, while new transmission typically takes five to ten years or more. Put a different way, you can build the pub a lot faster than the brewery.
We’ve seen this film in London. A few years back, parts of West London were warned that new housing developments could wait years for a grid connection because Data Centres had already taken up the available capacity. Nobody wants that conversation in Western Sydney or Brisbane.
Power is now a procurement workstream, not a utility bill. Power Purchase Agreements (PPA), cap contracts and firming arrangements need energy contracting skills that most Data Centre and IT teams simply don’t have. Somebody has to own it.
Your colocation price is going to change. If you’re a tenant rather than an operator, expect firming costs to find their way into your rate card. Read your contracts now, particularly the power pass-through and change-in-law clauses, before renewal time reads them for you.
Location matters more than ever. Because cover must sit in the same NEM region, the maths on where you place capacity, and how quickly you can get it energised, has changed.
Flexibility becomes a feature. Demand response counts towards firming. AI training workloads that can shift to sunny middays or quieter nights aren’t just greener; they may well be cheaper to cover. That’s an architecture decision, not a facilities one.
Your AI business case needs a real power number. Too many AI programmes assume compute is cheap and power is someone else’s problem. Under these rules it’s neither. Put firmed power costs into the business case from the start, not after the board has said yes.
Don’t wait for the fine print. The size thresholds haven’t been set, and the AEMC still has to run its consultation. Federal legislation is being targeted for early 2027. But Data Centre projects take years, and the decisions made in 2026 are the ones these rules will judge.
Last orders
Here’s where I’ve landed. Bring your own power is the right principle. Australia wants the Data Centre investment, and the jobs and AI capability that come with it, but not at the cost of households paying more for their electricity. Operators that treat this as an engineering and commercial programme, rather than a compliance box, will connect faster, contract better and look far more attractive to the hyperscalers and enterprises queuing for capacity.
Those who leave it until the rules are final may end up explaining to their board why the shiny new hall is fitted out, ready and sitting unpowered.
How is your organisation planning for firmed power? Tell me in the comments.
Australia’s energy rule-maker is weighing a request from Chris Bowen to make large Data Centres back their electricity use with firmed supply from the same grid region, because industry modelling warns that new Data Centres connecting without new supply could add about A$40 billion to power costs, most of it paid by households and businesses.
We explains what “bring your own power” means for operators, colocation tenants and AI business cases, and why the decisions made now will decide who connects first.
The Bushey Data Centre Practice provides independent, client-side support to organisations building, buying or running Data Centre capacity. We help:
- Enterprises and Government Departments procure hosting and colocation, plan fit-outs and migrate safely.
- Colocation and Data Centre operators resolve internal challenges, strengthen governance and deliver expansion programmes on time.
- Organisations going through change merge, separate or consolidate their Data Centre estates as part of M&A activity.
Every engagement is delivered using our proprietary Transformation framework. It brings Project Management, Change Management and Governance together, so power, permits and people are managed as seriously as the build itself. Our focus is always the business benefit: taking complex programmes through to results, not just to plan.
We’re a specialist boutique consultancy based in Australia with reach across APAC. Because we’re independent, we sit on your side of the table, with no products to sell and no vendor to protect.
#DataCentres #EnergyTransition #AustralianEnergy #AIInfrastructure #TechnologyTransformation